Way Ahead In Corrosion Control

Brent Pipeline

Pipeline cathodic protection retrofit using anodes built into stabilization mattresses

Brent_Pipeline4.jpg

Deepwater supplied Retromats and Retroclamps to protect 12 km of pipeline for 15 years

In 2010, a cathodic protection survey showed that two sections at each end of a 148 km pipeline in the North Sea had “low structure potentials”. In 2012, Deepwater installed CP retrofits on those sections, which were each at a depth of about 100 meters. The pipeline to be protected was 36” nominal pipe with a 7mm asphalt coating and a 2.25” thick concrete weight coat. To boost the cathodic protection, a total of 16 Retromats and Retroclamps were used in two groups of eight; these were placed within “hot spots” at either end of the pipeline, each 6 kilometers long. 

Deepwater’s Retromats, which are concrete stabilization mattresses with anode arrays cast inside, were used as the CP source. They were delivered as empty shells and anodes, and were assembled on-site by local crews. The shells were snapped together, the cables were connected and concrete was poured to embed the anodes within the mat.

Retromat info

Brent_Pipeline10.jpg
Brent_Crane.jpg
Brent_Pipeline7.jpg

Installation

The Retromats were transported via work boat and deployed using ROVs to position the mats into place. The mats were electrically connected to the pipeline with Retroclamps, which were also placed by ROV. The clamps use a screw-in bit that penetrates the concrete coat without harming the pipe. A continuity check confirmed that the electrical connection was made and that the pipeline was protected.

The installation was problem-free, completed on time and within budget, and the installation contractor stated that the Retromat installation didn’t cause any undue concerns. The Retromats will provide fifteen years of protection for the pipeline.

No related download nodes

Related Content

Deepwater supplied Retromats and Retroclamps to protect 12 km of pipeline for 15 years.

 In 2010, a cathodic protection survey showed that two sections at each end of a 148 km pipeline in the North Sea had “low structure potentials”. In 2012, Deepwater installed CP retrofits on those sections, which were each at a depth of about 100 meters. The pipeline to be protected was 36” nominal pipe with a 7mm asphalt coating and a 2.25” thick concrete weight coat. To boost the cathodic protection, a total of 16 Retromats and Retroclamps were used in two groups of eight; these were placed within “hot spots” at either end of the pipeline, each 6 kilometers long. 

Deepwater’s Retromats, which are concrete stabilization mattresses with anode arrays cast inside, were used as the CP source. They were delivered as empty shells and anodes, and were assembled on-site by local crews. The shells were snapped together, the cables were connected and concrete was poured to embed the anodes within the mat.

Retromat info

 

The Retromats were transported via work boat and deployed using ROVs to position the mats into place. The mats were electrically connected to the pipeline with Retroclamps, which were also placed by ROV. The clamps use a screw-in bit that penetrates the concrete coat without harming the pipe. A continuity check confirmed that the electrical connection was made and that the pipeline was protected.

The installation was problem-free, completed on time and within budget, and the installation contractor stated that the Retromat installation didn’t cause any undue concerns. The Retromats will provide fifteen years of protection for the pipeline.